Team:Newcastle/Timetable

From 2009.igem.org

(Difference between revisions)
Line 476: Line 476:
| Team rosters due  
| Team rosters due  
| Jen and Neil
| Jen and Neil
-
| <SPAN style="COLOR: #59E817">Done</SPAN> ?
+
| <SPAN style="COLOR: #59E817">Done</SPAN>
| v
| v
|-
|-

Revision as of 16:44, 21 October 2009


Timeline of Events

Team Newcastle 2009 iGEM 10-09-09 IMG 1062.JPG

The table below shows all of the tasks that need to be completed before the iGEM Jamboree in Boston, USA

Dates Tasks Task Assigned To Status No Change in Dates
05/02/2009 – 26/02/2009 Shorlist feasible projects Matthew Done -
12/02/2009 – 20/02/2009 IGEM Internal Wiki Setup Dan Done -
12/02/2009 – 13/02/2009 Apply for funding – Matthew Robinson Mathew Done -
12/02/2009 – 16/02/2009 Apply for funding – Arunkumar Arun Done -
12/02/2009 – 13/03/2009 Apply for funding – Jessica Jessica Done -
16/02/2009 IGEM 2009 registration opens Jen and Neil Done -
17/02/2009 – 23/02/2009 Getting familiar with MediaWiki All Done -
19/02/2009 Score all ideas for feasibility Jessica Done -
23/02/2009 – 08/03/2009 Getting familiar with Biobrick standards and some characterized Biobricks All Done -
23/02/2009 – 09/03/2009 IGEM Internal Wiki initial design is finished. Meeting notes, timelines and initial ideas are entered to the wiki Craig Done -
25/02/2009 Create front page of the wiki (IGEM's) Goksel Done -
26/02/2009 – 12/03/2009 Decide on the IGEM project all Done -
03/03/2009 Inspect other awards Craig Done -
05/03/2009 – present Allocate sub-projects/jobs All Done -
05/03/2009 – 19/03/2009 Decide on the project title All Done -
05/03/2009 – 26/03/2009 Design the project logo Hanny Done -
12/03/2009 – 01/08/2009 Design of modelling related sub-projects/tasks Goksel Done v
19/03/2009 Review of registration. Make sure everything is done. Jen and Neil Done -
20/03/2009 – 20/04/2009 Easter Vacation Arun: 4 weeks - Matthew: Last week - Craig: 1 week Done -
20/03/2009 – 20/06/2009 Create flyers for sponsors Mathew Done -
26/03/2009 - 10/10/2009 Implementation of modelling related sub-projects/tasks James, Goksel and Hanny Done v
26/03/2009 – 03/08/2009 Find Sponsors Mat/Arun Done -
31/03/2009 IGEM 2008 registration closes; Team registration fee due Jen and Neil Done v
01/04/2009 – 03/04/2009 IGEM wiki creation Mathew/James Done -
11/10/2009 Review of modelling tasks Hanny Done -
25/04/2009 – 30/04/2009 Review of BioBrick standards Arun Done -
25/04/2009 provisional sequentia tutorial all Done -
20/06/2009 – 21/06/2009 IGEM Workshop, Europe Jen Done v
01/07/2009 – 21/10/2009 Outline and detail a new approach to an issue of Human Practice in synthetic biology as it relates to your project, such as safety, security, ethics, or ownership, sharing, and innovation. [GOLD 1] all N/A N/A
24/06/2009 - 31/08/2009 Help another iGEM team by, for example, charactering a part, debugging a construct, or modeling or simulating their system [GOLD 2] all Done -
11/05/2009 Start revision period Arun,Jessica, Mathew Done v
11/05/2009 – 14/05/2009 Create the sequence to be synthesized according to the standards [BRONZE 1] Arun Done v
15/05/2009 Send the DNA sequence to be synthesized Arun Done v
06/2009 BioBrick parts sent to teams all Done -
28/05/2009 Review the dates of Jamboree for booking the flights and hotels. Goksel Done -
20/07/2009 Book the flights and hotel rooms Jen and Neil Done -
01/06/2009 – 12/06/2009 Exam Period Arun,Jessica, Mathew Done v
15/06/2009 Preliminary team rosters due Jen and Neil Done -
29/06/2009 – 22/07/2009 Lab refresher training All Done v
26/06/2009 Goksel - PhD:Application for Research Project Approval Form to be submitted Goksel Done v
29/06/2009 – 31/08/2009 Lab work Mathew, et al. Done -
30/06/2009 – 01/10/2009 The synthesized sequence is delivered to us all Done -
01/07/2009 – 21/10/2009 Lab notebook on IGEM wiki Arun Done -
01/07/2009 - 21/07/2009 Apply for visas All Done v
28/07/2009 – 15/08/2009 Familiarise with sequencing programs (Sequencher, Clone manager) all Done v
15/07/2009 Goksel - PhD project proposal presentation Goksel Done v
20/07/2009 – 25/09/2009 T-shirts are designed Hanny Done -
01/08/2009 Team project descriptions due Jess Done v
01/08/2009 – 27/08/2009 MSc thesis writing Craig and Hanny Done v
01/08/2009 – 06/10/2009 Characterize or improve an existing BioBrick Part or Device that was distributed via the iGEM BioBrick Parts collection, and enter this information back on the Registry. [GOLD 4] Jessica Done -
03/08/2009 – 01/10/2009 T-shirts are bought Hanny Done -
10/10/2009 IGEM Wiki review Mat Done -
05/08/2009 – 11/10/2009 Enter information detailing at least one new standard BioBrick Part or Device in the Registry of Parts [BRONZE 2] Hanny Done -
10/08/2009 - 10/10/2009 T-shirts are printed Hanny Done -
18/10/2009 IGEM Wiki review Goksel Done -
19/08/2009 – 06/10/2009 Develop and document a new technical standard [GOLD 3] Jessica - Craig N/A N/A
24/08/2009 – 20/10/2009 Demonstrate that at least one new BioBrick Part or Device of your own design and construction works as expected [SILVER 1] Arun Done -
28/08/2009 MSc Thesis submitted Craig and Hanny Done v
31/08/2009 – 15/10/2009 Characterize the operation of at least one new BioBrick Part or Device and enter this information on the Parts or Device page via the Registry of Parts (see BBa_F2620 for an exemplar). [SILVER 2] Jessica Done -
31/08/2009 – 16/10/2009 Model refinement Done - v
01/10/2009 Group meeting to discuss presentation all Done -
07/09/2009 – 10/10/2009 Design the poster [BRONZE 3 - a] Hanny Done -
10/09/2009 – 17/10/2009 Print the poster and pick it up [BRONZE 3 - a] Jessica Done -
08/10/2009 Group meeting to put presentation ideas together all Done -
15/09/2009 Everyone to apply for ESTA (US Visa) all Done -
17/09/2009 Jamboree attendance fee due Jen and Neil Done v
21/10/2009 Finish IGEM wiki [BRONZE 5] Mathew Done -
19/09/2009 Check if we need to make a request for variance Arun Done -
19/09/2009 – 26/09/2009 Create EMBL and FASTA files for Biobricks Hanny Done -
28/09/2009 Send the parts to the registry Jen and Neil Done v
01/09/2009 Track selection internal deadline Goksel Done -
01/09/2009 Project abstracts internal deadline Craig Done -
01/09/2009 Team rosters internal deadline Arun Done -
25/09/2009 Request for variance due (notice and description of any use of non-standard parts or devices schemes due Arun Done v
25/09/2009 Track selection due Goksel Done v
25/09/2009 Project abstracts due Craig Done v
15/09/2009 Team rosters due Jen and Neil Done v
16/10/2009 Check Wiki for fine tune Arun and James Done -
16/10/2009 Presentation fine tune and drafting all Done -
21/10/2009 [TBD] Project and part documentation due, including documentation for all medal criteria. Successfully complete and submit a Project Summary form [BRONZE 5] Done -
21/10/2009 BioBrick Part DNA needs to be received by the Registry [BRONZE 6] Neil and Jen Done v
21/10/2009 Enter EMBL and FASTA files for Biobricks on IGEM website Neil and Jen Done v
21/10/2009 IGEM Wiki is closed Mat - v
30/10/2009 – 02/11/2009 Bring the poster to the Jamboree Jessica - v
29/10/2009 – 04/11/2009 Competition Jamboree, MIT, USA all - v
30/10/2009 – 02/11/2009 Present a Poster and Talk at the iGEM Jamboree [BRONZE 3 - b] all - v



News

Events

Social Net

  • Newcastle iGEM Twitter
  • Newcastle on Facebook
  • Newcastle Youtube Channel