Timeline of Events


Team Newcastle 2009 iGEM 10-09-09 IMG 1062.JPG


The table below shows all of the tasks that need to be completed before the iGEM Jamboree in Boston, USA

Dates Tasks Task Assigned To Status No Change in Dates
05/02/2009 – 26/02/2009 Shorlist feasible projects Matthew Done
12/02/2009 – 20/02/2009 IGEM Internal Wiki Setup Dan Done
12/02/2009 – 13/02/2009 Apply for funding – Matthew Robinson Mathew Done
12/02/2009 – 16/02/2009 Apply for funding – Arunkumar Arun Done
12/02/2009 – 13/03/2009 Apply for funding – Jessica Jessica Done
16/02/2009 IGEM 2009 registration opens Jen and Neil Done
17/02/2009 – 23/02/2009 Getting familiar with MediaWiki All Done
19/02/2009 Score all ideas for feasibility Jessica Done
23/02/2009 – 08/03/2009 Getting familiar with Biobrick standards and some characterized Biobricks All Done
23/02/2009 – 09/03/2009 IGEM Internal Wiki initial design is finished. Meeting notes, timelines and initial ideas are entered to the wiki Craig Done
25/02/2009 Create front page of the wiki (IGEM's) Goksel Done
26/02/2009 – 12/03/2009 Decide on the IGEM project all Done
03/03/2009 Inspect other awards Craig Done
05/03/2009 – present Allocate sub-projects/jobs All Done
05/03/2009 – 19/03/2009 Decide on the project title All Done
05/03/2009 – 26/03/2009 Design the project logo Hanny Done
12/03/2009 – 01/08/2009 Design of modelling related sub-projects/tasks Goksel Done
19/03/2009 Review of registration. Make sure everything is done. Jen and Neil Done
20/03/2009 – 20/04/2009 Easter Vacation Arun: 4 weeks - Matthew: Last week - Craig: 1 week Done
20/03/2009 – 20/06/2009 Create flyers for sponsors Mathew Done
26/03/2009 - 10/10/2009 Implementation of modelling related sub-projects/tasks James, Goksel and Hanny Ongoing
26/03/2009 – 03/08/2009 Find Sponsors Mat/Arun Done
31/03/2009 IGEM 2008 registration closes; Team registration fee due Jen and Neil Done
01/04/2009 – 03/04/2009 IGEM wiki creation Mathew/James Done
11/10/2009 Review of modelling tasks Hanny Ongoing
25/04/2009 – 30/04/2009 Review of BioBrick standards Arun Done
25/04/2009 provisional sequentia tutorial all Done
20/06/2009 – 21/06/2009 IGEM Workshop, Europe Jen Done
01/07/2009 – 21/10/2009 Outline and detail a new approach to an issue of Human Practice in synthetic biology as it relates to your project, such as safety, security, ethics, or ownership, sharing, and innovation. [GOLD 1] all
24/06/2009 - 31/08/2009 Help another iGEM team by, for example, charactering a part, debugging a construct, or modeling or simulating their system [GOLD 2] all Done
11/05/2009 Start revision period Arun,Jessica, Mathew Done
11/05/2009 – 14/05/2009 Create the sequence to be synthesized according to the standards [BRONZE 1] Arun Done
15/05/2009 Send the DNA sequence to be synthesized Arun Done
06/2009 BioBrick parts sent to teams all Done
28/05/2009 Review the dates of Jamboree for booking the flights and hotels. Goksel Done
20/07/2009 Book the flights and hotel rooms Jen and Neil Done
01/06/2009 – 12/06/2009 Exam Period Arun,Jessica, Mathew Done
15/06/2009 Preliminary team rosters due Jen and Neil Done
29/06/2009 – 22/07/2009 Lab refresher training All Done
26/06/2009 Goksel - PhD:Application for Research Project Approval Form to be submitted Goksel Done
29/06/2009 – 31/08/2009 Lab work Mathew, et al. Ongoing
30/06/2009 – 01/10/2009 The synthesized sequence is delivered to us all Done/ongoing
01/07/2009 – 21/10/2009 Lab notebook on IGEM wiki Arun Ongoing
01/07/2009 - 21/07/2009 Apply for visas All Done
28/07/2009 – 15/08/2009 Familiarise with sequencing programs (Sequencher, Clone manager) all Done
15/07/2009 Goksel - PhD project proposal presentation Goksel Done
20/07/2009 – 25/09/2009 T-shirts are designed Hanny Done
01/08/2009 Team project descriptions due Jess Done
01/08/2009 – 27/08/2009 MSc thesis writing Craig and Hanny Done
01/08/2009 – 06/10/2009 Characterize or improve an existing BioBrick Part or Device that was distributed via the iGEM BioBrick Parts collection, and enter this information back on the Registry. [GOLD 4] Jessica
03/08/2009 – 01/10/2009 T-shirts are bought Hanny Ongoing
10/10/2009 IGEM Wiki review Mat Ongoing
05/08/2009 – 11/10/2009 Enter information detailing at least one new standard BioBrick Part or Device in the Registry of Parts [BRONZE 2] Hanny
10/08/2009 - 10/10/2009 T-shirts are printed Hanny
18/10/2009 IGEM Wiki review Goksel Ongoing
19/08/2009 – 06/10/2009 Develop and document a new technical standard [GOLD 3] Jessica - Craig
24/08/2009 – 20/10/2009 Demonstrate that at least one new BioBrick Part or Device of your own design and construction works as expected [SILVER 1] Arun
28/08/2009 MSc Thesis submitted Craig and Hanny Done
31/08/2009 – 15/10/2009 Characterize the operation of at least one new BioBrick Part or Device and enter this information on the Parts or Device page via the Registry of Parts (see BBa_F2620 for an exemplar). [SILVER 2] Jessica
31/08/2009 – 16/10/2009 Model refinement
01/10/2009 Group meeting to discuss presentation all
07/09/2009 – 10/10/2009 Design the poster [BRONZE 3 - a] Hanny
10/09/2009 – 17/10/2009 Print the poster and pick it up [BRONZE 3 - a] Jessica
08/10/2009 Group meeting to put presentation ideas together all
15/09/2009 Everyone to apply for ESTA (US Visa) all Done
17/09/2009 Jamboree attendance fee due Jen and Neil Done
21/10/2009 Finish IGEM wiki [BRONZE 5] Mathew
19/09/2009 Check if we need to make a request for variance Arun Done
19/09/2009 – 26/09/2009 Create EMBL and FASTA files for Biobricks Hanny
28/09/2009 Send the parts to the registry Jen and Neil
01/09/2009 Track selection internal deadline Goksel Done
01/09/2009 Project abstracts internal deadline Craig Done
01/09/2009 Team rosters internal deadline Arun Done
25/09/2009 Request for variance due (notice and description of any use of non-standard parts or devices schemes due Arun Done
25/09/2009 Track selection due Goksel Done
25/09/2009 Project abstracts due Craig Done
15/09/2009 Team rosters due Jen and Neil Done?
16/10/2009 Check Wiki for fine tune Arun and James
16/10/2009 Presentation fine tune and drafting all
21/10/2009 [TBD] Project and part documentation due, including documentation for all medal criteria. Successfully complete and submit a Project Summary form [BRONZE 5]  ???
21/10/2009 BioBrick Part DNA needs to be received by the Registry [BRONZE 6] Neil and Jen
21/10/2009 Enter EMBL and FASTA files for Biobricks on IGEM website Neil and Jen
21/10/2009 IGEM Wiki is closed Mat
30/10/2009 – 02/11/2009 Bring the poster to the Jamboree Jessica
29/10/2009 – 04/11/2009 Competition Jamboree, MIT, USA all
30/10/2009 – 02/11/2009 Present a Poster and Talk at the iGEM Jamboree [BRONZE 3 - b] all