Team:Brown/Notebook Meetings/9-11-09
From 2009.igem.org
(Difference between revisions)
Line 10: | Line 10: | ||
- | + | '''iGEM Meeting''' | |
- | iGEM Meeting | + | |
- | + | ||
- | 8:00 AM: Gary reminds us of our responsibility. We need to plan this semester! | + | '''9/11/09''' |
- | + | ||
- | Adrian: Deadlines | + | '''SFH 218''' |
- | + | ||
- | + | *8:00 AM: Gary reminds us of our responsibility. We need to plan this semester! | |
- | + | **These next few weeks are the most important | |
- | + | ||
- | Gary | + | *Adrian: Deadlines |
- | + | *Jamboree is in 7 weeks! | |
- | + | *Wiki due date: 6 weeks. Adrian recommends we have it done in 5 weeks | |
- | Team 1 update | + | *Presentation practice should be started in 5 weeks |
- | + | *Data collection should be heavy these next few weeks | |
- | + | *Gary: | |
- | + | **Judging is done by a criteria. Criteria is available to us. | |
- | + | **Regular meetings: Friday 8AM in SFH 218 | |
- | Team 2 update | + | |
- | + | *Team 1 update | |
- | + | **Did not have any expression on the western blots | |
- | + | **Made new BL21 competent cells, however no transformations | |
- | + | **Test competence of cells | |
- | + | **End of next week goal: protein expression | |
- | + | ||
- | + | *Team 2 update | |
- | + | **Made all of the constructs needed | |
- | + | **Agr-GFP ligated | |
- | + | **Trg-EnvZ | |
- | + | **Signal Pep-GFP | |
- | Team 3 update | + | **Trouble is transforming into S. epi |
- | + | **Looking for new vectors – talking to same guy that sent us PLM6 | |
- | + | **Primers designed for adapting to new vector | |
- | + | **Will’s computer program worked; designed for Tar | |
- | + | **He is concerned about mutagenesis – time consuming | |
- | + | **Submit for synthesis | |
- | Everybody: come up with a week-by-week goal sheet. | + | **Will will pick 5 candidates |
- | The team is meeting next Tuesday at 8AM. | + | |
+ | *Team 3 update | ||
+ | **We have OmC-RFP and Taz in pNoTat | ||
+ | **Ashley did stratagene, however her positive control plate did not work | ||
+ | **We can test with aspartate | ||
+ | **Will also test ribose binding protein | ||
+ | **If double transformation does not work, sequential transformation | ||
+ | |||
+ | *Everybody: come up with a week-by-week goal sheet. | ||
+ | |||
+ | *The team is meeting next Tuesday at 8AM. |
Latest revision as of 01:58, 22 October 2009
iGEM Meeting
9/11/09
SFH 218
- 8:00 AM: Gary reminds us of our responsibility. We need to plan this semester!
- These next few weeks are the most important
- Adrian: Deadlines
- Jamboree is in 7 weeks!
- Wiki due date: 6 weeks. Adrian recommends we have it done in 5 weeks
- Presentation practice should be started in 5 weeks
- Data collection should be heavy these next few weeks
- Gary:
- Judging is done by a criteria. Criteria is available to us.
- Regular meetings: Friday 8AM in SFH 218
- Team 1 update
- Did not have any expression on the western blots
- Made new BL21 competent cells, however no transformations
- Test competence of cells
- End of next week goal: protein expression
- Team 2 update
- Made all of the constructs needed
- Agr-GFP ligated
- Trg-EnvZ
- Signal Pep-GFP
- Trouble is transforming into S. epi
- Looking for new vectors – talking to same guy that sent us PLM6
- Primers designed for adapting to new vector
- Will’s computer program worked; designed for Tar
- He is concerned about mutagenesis – time consuming
- Submit for synthesis
- Will will pick 5 candidates
- Team 3 update
- We have OmC-RFP and Taz in pNoTat
- Ashley did stratagene, however her positive control plate did not work
- We can test with aspartate
- Will also test ribose binding protein
- If double transformation does not work, sequential transformation
- Everybody: come up with a week-by-week goal sheet.
- The team is meeting next Tuesday at 8AM.